You will need the following tools:
1200mm level
Cordless drill
5mm drill bit
8mm drill bit
13mm ring spanner
Stud finder
Measuring tape
Masking tape and pencil
Masonary drill and 10mm bit if fixing to brickwork
​STEP 1
-
Locate timber wall framing using a stud finder
-
You'll need two studs approximately 450mm to 600mm apart
-
Mark height of top rack approximately 1400 from the floor
-
Mark height of bottom rack approximately 300mm from the floor
-
Ensure marks are level
​​
​STEP 2
-
Drill 5mm pilot hole in centre of timber stud approx 60mm deep and install hanging bolt
-
Ensure 35mm of hanging bolt protrudes from the wall
​
-
If fixing to brickwork, drill a 10mm hole and insert the orange rawl plug supplied
​STEP 3
-
Accurately mark the centre of the hanging bolts on the back edge of the Rod Rack
​STEP 4
-
Repeat for all four hanging bolts
​STEP 5
-
Drill a 5mm pilot hole through the back of the Rod Rack - A straight edge on top helps ensure the hole is drilled straight
​STEP 6
-
Enlarge Pilot hole to 8mm
​STEP 7
-
Slide Rod Rack over hanging bolts and secure with flat washer and nut.
​STEP 8
-
Tighten nut with 13mm ring spanner
Place rods in Rod Rack
bottom of page